Our project to construct a new sewage treatment system for a valued client in Herstmonceux is progressing well, with the 14.5m x 11m x 3m deep excavation completed and the RC base cast last week. On Tuesday, the three 13m long BioDisc units were delivered to site and carefully craned into position. The next step is to fill the tanks with “grey” water supplied by our valued client, County Clean, before backfilling around the tanks with mass concrete. Congratulations to Guy, Werner and the team on another exceptional piece of work to date.