Sector:Potable Water
Client:The Sutton & East Surrey Water Company
Year of Project:2016 - 2018
Project Value:£8,500,000
Duration:130 weeks

Design and construction works at the site of the existing Woodmansterne WTW to expand the capacity to treat 50Ml/day and included the following scope:

  • New 60m x 30m x 6m deep RGF structure including chlorine contact tank, supporting a 9m high steel framed building
  • Extension to treated water pumping station
  • New standby generator building
  • Site pipework modifications (150mm-900mm dia.) – approx. £1m
  • Ducting to link new to existing treatment processes
  • Foul and surface water drainage
  • Diversion of services to facilitate new installations
  • Hard and soft landscaping