Sector:Coastal, River and Environmental
Client:Pevensey & Cuckmere Water Level Management Board
Year of Project:2025
Project Value:£607,000
Duration:18 weeks

Following a successful smaller project for the same Client in 2023 and some proactive ECI, Thorne was asked to work alongside Aquatic Control Engineering Ltd on a project to help control the height of the water throughout the Pevensey Levels.  The works involved the following:

  • Removal and replacement of a 900mm diameter culvert to improve access to the levels
  • Construction of temporary cofferdams up- and downstream
  • Installation of an over-pumping system to create a dry and safe working area
  • Installation of permanent steel sheet piles to accommodate the solar powered automated tilting weirs
  • Installation of five new tilting weirs and access steps / bridges.

We had our Board Meeting today and the landowner Board Members were full of praise for you and your team. They said you were quite polite, considerate and helpful.

Thank you for everything you and your team did to make them only have praise for Thorne employees.

Revai Kinsella, Water Management Alliance

Share this project