Woodmansterne WTW

Woodmansterne WTW

The project at Woodmansterne WTW has made real progress over the last couple of months. The Rapid Gravity Filter building brickwork and blockwork is now complete as well as the CCT pipework and the Sample Building roof is due to be installed in the new year.

All concrete works in the Treated Water Pumping Station is finished with the vehicle access slab left to complete. Work is continuing on the Standby Generator Building, where the brickwork and blockwork is halfway to completion. We will then follow on with the roof installation.